EPTT, Hydro Power, Steel Manufacturing and Telecomunication by Alamdar Engineering (Pvt.) Ltd.

Project Accomplished:

PROJECT - 4

 

CIVIL WORKS, CONSTRUCTION, ERECTION, TESTING & COMMISSIONING OF 220 /132KV SUBSTATION
AT VEHARI.

CLIENT:

PAKISTAN WATER & POWER DEVELOPMENT AUTHORITY (WAPDA).

CONTRACT:

MAIN CONTRACTOR

 

 SCOPE OF WORK:

 

 

 

 

 

 

 

 

 

 

 

 

 

 Installation of breaker 220KV bays with 2 Nos.
220/132KV 300MVA auto transformers and 10
Nos. 132KV bays with double bus system with
bus coupler and 1 Nos. 132 / 11 KV 10 MVA
Transformer.

Clearing, Grubbing of the complete site area for bushes, vegetation trees,
Roots and weeds etc.

Site leveling, Cutting / Filling, Compaction

Bulk Excavation & Structural Excavation

Construction of complete civil works I.e., RCC
foundations for transformers & switchyard
Equipment

Construction of Control house building

 

Installation of Earthing system.

 

Erection of gantries, yard equipment support
Structures. 

 

Stringing of bus bar rigid/conductors and shield
Wire and interconnection between equipment. 

 

Erection / installation of 2 Nos. 220/132KV
transformers 1 No. 132/11KV transformer, 220KV
& 132KV switchyard equipment with indoor
Control/relay panel and AC/DC system.

Control & protection wiring.

Testing and commissioning. 

STATUS:

 Commissioned in March, 1999.