EPTT, Hydro Power, Steel Manufacturing and Telecomunication by Alamdar Engineering (Pvt.) Ltd.

Project Accomplished:

PROJECT -3

CIVIL WORKS, ERECTION, TESTING & COMMISSIONING OF 500/ 220 KV SUBSTATION PESHAWAR – SHIEKH MUHAMMADI. 

CLIENT: 

PAKISTAN WATER & POWER DEVELOPMENT AUTHORITY.

CONTRACT:

MAIN CONTRACTOR

SCOPE OF WORK

 

 

 

 

 

 

 

 

 

 

 

 

 

Transportation of complete sub station
Equipment including 7. Nos. Auto Transformers
(unit wt. 110 tons) from Sahiwal to Peshawar
(Distance = 650 Km).

Clearing and Grubbing of the complete site area for bushes, vegetation trees,
Roots and weeds etc.

Site leveling, Cutting / Filling, Compaction of
Yard measuring 520 x 420 Meters.

Bulk & Structural Excavation

Construction of RCC Foundation of Transformers,
firewalls, RCC foundation of outdoor & indoor
Equipments.

Construction of Control House Building &
Mechanical services building.

Construction of fire fighting service building and
Erection of fire fighting equipments.

Construction of carpeted roads, walk ways.

Construction of drainage system for disposal
of rain flood water.

 Erection / Installation of 500 / 220 KV. Auto
Transformers with Indoor / Outdoor equipment.

Stringing of bus bar conductors and shield wire
and interconnections between equipment and
terminal tower.

 STATUS: 

Commissioned in February 1996-1997