Project Accomplished:
PROJECT -3  | 
                          CIVIL WORKS, ERECTION, TESTING & COMMISSIONING OF 500/ 220 KV SUBSTATION PESHAWAR – SHIEKH MUHAMMADI.  | 
                        
CLIENT:  | 
                          PAKISTAN WATER & POWER DEVELOPMENT AUTHORITY.  | 
                        
CONTRACT:  | 
                          MAIN CONTRACTOR  | 
                        
SCOPE OF WORK 
 
 
 
 
 
 
 
 
 
 
 
 
  | 
                          Transportation of    complete sub station   | 
                        
Clearing and    Grubbing of the complete site area for bushes, vegetation trees,  | 
                        |
Site leveling,    Cutting / Filling, Compaction of   | 
                        |
Bulk & Structural Excavation  | 
                        |
Construction of RCC    Foundation of Transformers,  | 
                        |
Construction of Control House Building    &   | 
                        |
Construction of    fire fighting service building and  | 
                        |
Construction of carpeted roads, walk ways.  | 
                        |
Construction of    drainage system for disposal   | 
                        |
 Erection /    Installation of 500 / 220 KV. Auto   | 
                        |
Stringing of bus    bar conductors and shield wire  | 
                        |
STATUS:  | 
                          Commissioned in February 1996-1997  |